Can I request monitoring observations with standalone ACA?
Posted by Suzanna Randall, Last modified by Sarah Wood on 03 April 2018 04:41 PM

Yes, you may request monitoring observations with the standalone ACA.

When setting up time constraints in a standalone ACA scheduling block, make sure that the LAS is set so that only the ACA is used. If the TP array is also selected, you will receive an error when  validating your project. You cannot set up time constraints for multiple configurations.